Case Histories
Click on a project below for more details.
Construction Management - Laboratory &
Offices
Construction Management - Pharmaceutical
Powder ops
Manufacturing Improvement - Medical Product
Automated Product
Manufacturing Improvement - Medical Product
- Batch Processing
Specification Development - Pharmaceutical
- Co-Packed Product
Construction Management - Laboratory &
Offices
Background: A Contactor/Engineering company was awarded a
Not-to-Exceed $4.9MM, fast-track design build contract with a six
month deadline. Failure to meet the deadline would result in a $30,000/week
penalty for every week delayed. Any savings on the base contract
would be shared between the owner and the GC.
Scenario: Due to the tight schedule the GC immediately began
demolition and assigned an in-house engineer as PM. Action Plus
Project Management was brought in as Project Manager 4 weeks after
demolition started.
Action Plus Project Management reviewed the existing Project Schedule
and observed the plan had major tasks with little detail, there
were no relationships identified between tasks and only initial
resources identified.
Demolition was being carried out by three trades with little definition
and lack of clarity. Plans were sketchy and lacked much detail.
By the end of the fourth week of demolition, the work was projected
at six weeks behind the plan and the demolition work scope was expanding.
APPM gathered the GC's Engineer, Project Superintendent and Field
Supervisor for a four hour review. Utilizing their knowledge and
expertise, the goals were defined in detail and a Work Breakdown
Structure developed. The group then developed a Network diagram
and estimated durations for all tasks. APPM performed network calculations
which showed the projected end date 4 weeks later than the deadline.
A quick review of risks indicated a potential for an additional
two to four week delay. A goal was set to "crash" the
program by 8 weeks. Brainstorming with the team, APPM developed
a strategy and schedule all agreed was achievable. Many unplanned
activities arose. Through frequent review and corrective action,
and utilizing the expertise of sub-contractors, the project was
substantially completed one week before the deadline avoiding the
late penalty.
Results: CO issued one week before deadline avoiding penalties.
Bonus: Utilizing VE techniques and competitive bidding, the base
work was completed $500,000 under budget earning the GC a handsome
bonus.
Back to top
Construction Management - Pharmaceutical
Powder Mixing & Filling
Background: A Pharmaceutical manufacturer made a choice to consolidate
operation from two locations approximately 15 miles apart. The manufacturer
had relocated most operations with one or two exceptions, plus they
had materials stored in the facility they were vacating. To realize
the complete benefit of consolidation the owner was seeking to divest
the vacant facility.
Scenario: Management was focused on making year end sales
when they realized the facility they were not completely vacated
from was sold. The purchaser needed the space and a condition of
sale was that it be vacated within one month. The manufacturer was
not prepared to move the operation.
Action Plus Project Management was engaged as a Project Manager.
The objective was to identify a location in the new facility, design
the space and engage a contractor to complete the necessary construction
within 3 weeks.
On day one Action Plus Project Management visited the site being
vacated, gathered details necessary regarding the manufacturing
equipment and space requirements and immediately began to search
for Construction Contractors. On day two a visit was made to the
receiving site. After touring the site with the company management
a location within the building was identified. On day three, line
layouts and room layouts were prepared and contractors were scheduled
to make a site visit. Each contractor was given the layout and a
two week deadline for completion of all construction including electrical,
plumbing, ceilings, lighting, wall construction and epoxy painting.
Company purchase orders were released by the end of week one. Action
Plus Project Management visited the site frequently and was in close
contact with the GC to ensure both the schedule and scope of work
was complete. Construction was complete by the end of the second
week with all interior surfaces finish epoxy painted the day before
equipment was moved in.
Results: Two days later all equipment was made operational
allowing the company to restock the Finished Goods Warehouse before
depleting inventory.
Back to top
Manufacturing Improvement - Medical
Product Automated Manufacturing
Background: A manufacturer had invested $2,000,000 in a "state
of the art" Surgeon's Glove Line. To lower investment costs,
the line had been designed by "in-house" engineers who
also supervised the fabrication and installation. After the line
was installed, in-house engineers and operators attempted to operate
the line. After two years the line had been operated four days.
Each attempt to operate the line resulted in catastrophic failure
of the equipment.
Scenario: The fabricator and installer insisted the line
was built to the company's specifications and under their supervision
and hence they would not guarantee the performance of the line.
The principal of APPM, at the time employed by the company in a
different location, was brought in to assess the situation and recommend
a solution.
The principal of APPM met with management, engineering, maintenance
and production operators over a one week period. When not meeting
with personnel, the equipment was reviewed and inspected. The line
was a multi station unit, twelve feet wide, two stories high and
one-hundred and forty feet long. The line consisted of a series
of automated dipping stations and heating stations ending with a
second story oven 140' long. The environment was hot and humid.
Machine operation was controlled by a series of PLCs linked together
with a solid state sensors and controls.
The goal was to make the line produce high quality surgeon's gloves
reliable 24 hours a day, 7 days a week for three month intervals
with OEE of 98%. The principal of APPM agreed to act as the on-site
Project Manager.
A five step program was recommended and implemented to make the
line operational at the levels required: The plan would take nine
months and require an investment of $250,000. The plan addressed:
Equipment redesign, Equipment installation alignment, Operator Training,
Implementation of a Preventive Diagnostic & Maintenance program,
Re-aligned Maintenance Stores Program.
Results: Nine months following the project start the line
was started up and operated continuously for 3 months producing
high quality surgeons' gloves. With the successful completion of
this project, a plant wide "continuous improvement" process
was initiated.
Back to top
Manufacturing Improvement - Medical Product
batch processing
Background: A manufacturer critical medical products was experiencing
problems. The manufacturer had grown their business to command an
80% market share at a handsome profit margin. The product line contributed
more than 50% of the overall profit for the business although it
was only 20% of sales.
Scenario: Production problems had disrupted the company's
ability to meet market demand and competitors swiftly filled in
the shortfall. Market share collapsed rapidly to 50%. The manufacturing
plant personnel indicated nothing had changed in the process, identifying
a "quality issue" attributed to an unidentified change
in process water quality at the final operation.
The principal of APPM was brought in to help identify the change
in process water and recommend a solution.
The principal of APPM observed the entire process including the
final operation and inspected the test records of the process water.
Water samples were taken and sent out for a critical analysis.
No obvious changes were noted from the period of high production
through the deterioration period. Discussions were held individually
with management, engineering, maintenance and production personnel.
The entire manufacturing process was reviewed including evaluation
of in-process quality at each stage of the multi-stage process.
All operations in the company were under heavy pressure to reduce
cost.
The goal was to return the plant to reliable production and return
to a market leadership position.
The principal of APPM identified a change in management philosophy
and the reward system for operators. There were no obvious changes
in any one operation. The new incentive system caused operators
to imperceptibly loosen quality standards. The production operators
at the final stop were the only ones not benefiting from the new
plan. They were not able to improve output.
Results: Incentives were revised to reward the workers only
if the operation goal was attained.
Back to top
Specification Development - Pharmaceutical
Co-packed product
Background: A marketer of OTC consumer products recently audited
by the FDA identified a critical need to bring their documentation
and quality systems on co-packed product into compliance quickly.
Action Plus Project Management worked with the marketer to prepare
specifications for use by receiving QC inspectors and also by purchasing
when establishing new co-packers.
Action Plus Project Management established formats and methodologies
to prepare specifications accurately and with minimal effort. Utilizing
digital photography Action Plus Project Management created specifications
showing inspection requirements in a visual manner which enabled
the marketer and the co-packers, all of whom have ESL employees,
to work to common standards that are easily recognizable.
Back to top
|